Gauteng Province Metro Municipality Annual Reports 2011–2025 Intelligence Portal v2
City of Ekurhuleni — Municipal Intelligence Portal · 2009–2025
Comprehensive performance, demographic, financial, economic and service-delivery data from official Annual Reports 2011/12–2024/25. All charts support hover tooltips and value label toggling.
Population 4.22M (2024/25) Revenue R49.3bn (2022/23) Unemployment 36.3% (2024/25) GVA R418bn (2023) Water MSL 99% (2023/24) Manufacturing GVA R99.6bn (2023)
Key Statistics — Ekurhuleni at a Glance
Population 2024/25
4.22M
from 2.84M in 2009
Area (km²)
1,975
Gauteng: 18,178 km²
Pop. Density / km²
2,137
vs Gauteng 588
Households 2023
1.27M
from 910K in 2010
Revenue 2022/23
R49.3bn
from R20.8bn 2011/12
Unemployment 2024/25
36.3%
from 18.1% in 2001
Total GVA 2023
R418bn
current prices
GVA Share of SA
6.5%
Current prices 2010

Population Growth · 2009–2025

Uses the latest restated figure available for each year, per report vintage: 2013–2014 IHS (2015/16 AR, uncontested) · 2015/16–2016/17 StatsSA T.1.2.2 (2017/18 AR, only source at that granularity) · 2017/18 IHS Regional eXplorer (2019/20 AR restatement supersedes the 2017/18 AR's own StatsSA figure of 3,453,603 — different vendor, not a same-method correction, flagged) · 2018/19 unchanged across 2019/20 & 2020/21 ARs · 2019/20–2021/22 restated in the 2022/23 AR — note: these values are suspiciously identical to the 2021/22 AR's prior-year figures shifted one year forward (e.g. 2022/23 AR's "2019/20"=3,804,747 equals 2021/22 AR's own "2020/21"), suggesting a column-label error in one of the two reports rather than a genuine restatement — used per restatement rule but flagged · 2022/23–2024/25 from the 2024/25 AR.

GVA Total Industries · 2021–2023 (R billion)

GVA Economic Activity by Sector

GVA by Sector · 2011/12–2023 (R billion, current prices) · latest restated per year

Sourced across 8 Annual Reports. Each year shown uses the latest restated figure available. 2019/20–2021/22 were restated in the 2021/22 AR (repeated in 2022/23 AR) at ~35–40% below every adjacent report's figures for the same sectors — this does not reconcile with the pre-2019/20 or post-2021/22 trend and looks like a scope/methodology error rather than a genuine correction, but per the "use latest restated" rule these are the values charted, flagged here rather than silently substituted. See the Data Quality table below for the full version history.
Years CoveredLatest Restatement InSource VintageTotal Industries (R'000)Note
2011/12–2014/152014/15 ARpre-2015 Regional eXplorerUsed as-is in original extraction; no later restatement found.
2015–2017 (calendar)2018/19 AR (repeats 2017/18 AR verbatim)Regional eXplorer 1417/18278,916,375 / 303,335,600 / 324,390,673No revision across the two reports that carry it.
2017/18–2018/19 (fiscal)2020/21 ARRegional eXplorer ~1946/2020320,952,103 / 338,248,145Supersedes the 2019/20 AR's own row-shifted extraction of the same two years (values differ by <1%) — later report used per restatement rule.
2019/20–2021/22 (fiscal) — used in chart2021/22 AR, repeated unchanged in 2022/23 AR (latest)Regional eXplorer 2236/2021226,302,694 / 218,035,789 / 230,919,710Charted per the "use latest restated" rule, but flagged: ~35–40% below every adjacent report's figures for the same sectors, and the series reverts back to the higher scale immediately after (2023/24 AR) — this pattern looks like a scope/methodology error rather than a genuine correction. Shown as primary data with this caveat, not silently smoothed.
2021–2023 (calendar)2024/25 AR (repeats 2023/24 AR verbatim)not stated in report text364,257,536 / 392,918,914 / 417,758,763Consistent with the pre-2019/20 high scale — reports reverted after the two anomalous editions rather than continuing the low scale.
Ekurhuleni vs Gauteng vs National — 2010
IndicatorEkurhuleniGautengNational
Geographic size (km²)1,92818,2131,221,246
Population2,873,99710,708,65949,780,934
Population density (per km²)1,490.72587.9840.76
Economically active population (%)48.6%50.8%33.6%
Number of households910,4503,397,85013,449,175
Annual per household income (R)151,687171,477123,570
Annual per capita income (R)49,48255,48034,237
Gini coefficient0.620.630.64
Formal sector employment759,2523,803,3669,392,253
Informal sector employment93,013468,8772,164,297
Unemployment rate (expanded)31.1%24.3%24.7%
People in poverty27.5%25.6%39.9%
Human Development Index (HDI)0.650.670.58
Total GVA 2010 (R million, current)137,980738,1222,176,598
Share of SA GVA (%)6.5%35%100%
Poverty gap (R millions)1,6535,91547,878
Index of Buying Power (IBP)0.080.341.00
GVA at constant 2005 prices (R million)67,211334,3861,092,865
GVA share — constant 2005 prices %7.6%37.4%100%
GVA growth 1996–2010 (% pa)2.7%3.8%3.3%
Description20012006201120162017
Total Population2,429,2532,734,5663,088,8803,461,4373,528,800
Economically Active Population (official)1,165,2821,303,8031,506,0471,685,4701,721,509
Not Economically Active1,263,9711,430,7631,582,8341,775,9671,807,291
Total Unemployed (official)370,507334,481453,697519,383558,301
Total Employment (Formal + Informal)796,942962,8521,054,9881,175,6631,198,485
Unemployment Rate (official)31.8%25.7%30.1%30.8%32.4%
Quality of Life · Survey Index 2009–2016
Indicator200920112013/142015/16
Satisfied with life as a whole (%)42%67%67%68%
Quality of Life Index (out of 10)6.035.755.966.18
Customer Satisfaction — Metro Benchmarking
Municipality2016 Score2017 ScoreChange
Cape Town70.3%68.5%-1.8%
Ekurhuleni58.0%59.8%+1.8%
Nelson Mandela Bay53.8%59.0%+5.2%
eThekwini61.2%57.8%-3.4%
Tshwane59.5%57.7%-1.8%
Johannesburg54.6%57.0%+2.4%
Manguang52.9%51.3%-1.6%
Buffalo City47.6%47.2%-0.4%
Industry Average59.3%
Historical Baseline · 2001–2011
YearPopulationSource
20012,431,668Census 2001
20072,688,144Community Survey 2007
20092,844,706Global Insight (IHS)
20112,722,896Census 2011
20122,800,000Estimate
Population Time Series · 2009–2025
Population 2009
2.84M
Population 2021/22
3.93M
restated, 2022/23 AR
Population 2024/25
4.22M
Unemployment 2024/25
36.3%
Housing Backlog 2024/25
20.2%
HIV Prevalence 2024/25
14.4%
Illiteracy 2024/25
5.0%
Low-skilled Employment
17.9%
2024/25

Unemployment, HIV & Housing Backlog · 2009–2025

Population growth trend is charted on the Overview tab. This chart tracks unemployment, HIV/AIDS prevalence and housing backlog over the same period.
Socio-Economic Indicators · Time Series (2022/23–2024/25)

Key Socio-Economic Indicators · 3-Year Comparison

Source: T 1.2.4 — Socio Economic Status, Annual Reports 2022/23–2024/25
YearPopulationPoverty %Unemployment %HIV/AIDS %Illiteracy %Housing Backlog %Low-Skilled Emp %Low-Income HHs %
20092,844,70627%33.0%6%
20102,873,99726%36.7%4%
20112,902,00824%30.1%27%3%
20123,178,47027.9%28.8%19%17.8%
2015/163,319,81529.4%10.68%9.7%
2016/173,386,53430.8%10.69%9.5%
2017/183,621,48432.4%10.73%9.1%288,433 units26.0%
2019/203,804,74733.9%14.4%8.2%
2020/213,858,14735.0%14.5%
2021/223,926,67737.1%5.9%
2022/234,090,76536.9%14.0%5.3%20.0%17.3%0.0080%
2023/244,155,61436.2%14.2%5.0%20.7%17.9%0.0073%
2024/254,221,94236.3%14.4%5.0%20.2%17.9%0.0065%
Population by Age Group · Master Time Series
Each year uses the latest restated figure available: 2013–2014 IHS (2015/16 AR, uncontested) · 2015/16–2016/17 StatsSA T.1.2.2 (2017/18 AR, only source at this granularity) · 2017/18–2018/19 IHS Regional eXplorer (2019/20 AR; 2017/18 supersedes the 2017/18 AR's own StatsSA figure — different vendor, flagged, not a same-method correction) · 2019/20–2021/22 IHS Regional eXplorer restated in the 2022/23 AR — flagged: identical to the 2021/22 AR's prior-year figures shifted forward one year, suggesting a column-label error rather than genuine restatement, used per restatement rule · 2022/23–2024/25 from the 2024/25 AR. 2016/17 has no separate IHS-vendor breakdown; StatsSA is the only source.
Age Group 2013 2014 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 2024/25
MaleFemaleTotal MaleFemaleTotal MaleFemaleTotal MaleFemaleTotal MaleFemaleTotal MaleFemaleTotal MaleFemaleTotal MaleFemaleTotal MaleFemaleTotal MaleFemaleTotal MaleFemaleTotal MaleFemaleTotal
00-04161,013161,643322,656163,143163,838326,981163,612164,315327,927165,193165,965331,158174,097171,715345,812174,167172,449346,616162,410161,187323,597162,076160,754322,830162,394160,931323,325163,855159,232323,087164,847161,143325,990166,230162,893329,123
05-09140,040140,167280,207144,965144,802289,768145,432145,273290,705149,539149,125298,664163,700159,601323,301165,895161,431327,326156,772157,713314,485158,215158,945317,160159,646160,005319,651165,104157,684322,788163,280156,305319,585162,102155,778317,880
10-14113,839114,758228,598118,511119,231237,742118,902119,618238,520124,497125,025249,522152,110152,586304,696159,630159,680319,310157,161160,222317,383158,152161,280319,431158,725161,883320,608174,670169,619344,289174,514169,312343,826174,610169,385343,995
15-19108,857112,212221,069108,613111,531220,144108,953111,870220,824109,073111,565220,637134,925139,205274,130136,171139,908276,079127,092129,659256,751133,070136,097269,166140,342143,614283,956158,215152,624310,839164,400159,431323,832168,100163,582331,682
20-24142,848141,020283,868140,091138,661278,752140,453139,010279,463136,679135,655272,334153,895152,725306,621151,523151,123302,646127,058126,820253,877124,533124,928249,461124,962125,318250,280140,505130,759271,264141,596131,660273,256143,833133,993277,827
25-29188,497173,276361,772189,707174,070363,777190,186174,501364,688189,377173,666363,043189,409176,025365,433188,534175,144363,678166,743157,678324,421163,537155,678319,216162,356154,599316,955183,823170,387354,210175,821161,390337,212173,106157,626330,732
30-34186,077161,949348,026190,609166,727357,336191,078167,154358,232194,672171,041365,712197,738175,786373,524201,800180,988382,788194,511170,673365,183193,037170,641363,678192,228170,370362,599199,972179,036379,009207,825185,967393,792211,399188,506399,904
35-39150,085128,267278,352157,178134,786291,964157,586135,164292,749164,741141,834306,574166,706135,901302,607173,406143,616317,021188,619157,366345,985191,826162,397354,223195,476167,609363,086192,878169,133362,012195,123172,628367,751196,075174,746370,821
40-44118,842100,185219,027122,088103,595225,683122,435103,915226,351126,119107,793233,912130,698109,145239,843136,884113,327250,211169,190138,750307,940172,628141,843314,471176,447145,509321,956174,914149,757324,671178,291153,389331,680182,066157,762339,828
45-4995,89585,260181,15498,93487,254186,18899,22787,515186,742102,33289,714192,04699,67385,032184,706104,77389,903194,676145,321123,682269,002148,170126,476274,646151,359129,317280,676156,582135,849292,431159,967139,216299,184163,809142,690306,499
50-5476,31072,938149,24778,02374,611152,63478,24474,822153,06780,18276,521156,70381,18676,573157,75983,03076,835159,865110,04598,341208,386115,220102,288217,508120,311106,567226,878127,239111,946239,185132,596116,591249,188137,541121,149258,690
55-5961,66660,206121,87263,76762,483126,25163,95362,664126,61765,92264,770130,69267,55870,481138,03969,44171,606141,04784,70782,662167,37088,56784,677173,24492,74686,901179,64896,60390,063186,666101,21192,923194,135105,83195,938201,768
60-6446,24845,29891,54647,76147,40195,16247,90647,54695,45249,49549,69299,18752,34157,900110,24153,79659,623113,41961,32067,487128,80863,61269,227132,83966,11770,945137,06267,97071,106139,07770,82973,274144,10374,03275,555149,586
65-6931,83132,87964,70933,50834,45167,95933,62034,56168,18135,27236,23571,50740,65544,83885,49341,41146,87488,28542,66251,07493,73644,08053,16597,24445,77855,291101,06947,63254,878102,51049,50956,947106,45551,49859,075110,573
70-7419,67222,67042,34220,70923,71044,41920,78423,79244,57621,89724,91146,80825,03329,58454,61826,97331,47358,44629,33934,51663,85530,20036,13766,33730,96738,02568,99230,76438,05068,81432,24239,94772,18933,78941,97175,761
75+16,09227,31343,40516,88728,69145,57716,96228,75945,72117,82130,21348,03520,69033,97454,66321,60835,65257,26023,66740,30063,96724,89241,79866,69026,32243,61369,93626,77743,13869,91628,17045,26773,43729,64947,62377,273
Total1,657,8121,580,0393,237,8511,694,4941,615,8423,310,3361,699,3331,620,4793,319,8151,732,8111,653,7253,386,5341,850,4151,771,0693,621,4841,889,0411,809,6333,698,6741,946,6171,858,1303,804,7471,971,8151,886,3323,858,1472,006,1781,920,4993,926,6772,107,5041,983,2614,090,7652,140,2232,015,3914,155,6142,173,6702,048,2724,221,942
Neighbourhoods Overview · Longitudinal Household & Population Dynamics
Township, informal-settlement and 2016/17-town figures are the only breakdowns disclosed at that geographic granularity across all 13 available Annual Reports — this is a genuine source gap, not an extraction omission. Later reports (2021–2023) only disaggregate to main-town level.
Settlement / Region 2016/17 2021 2022 2023
HouseholdsPopulationHouseholdsPopulationHouseholdsPopulationHouseholdsPopulation
Main Towns & Commercial Centres
Alberton39,000125,000221,379738,472229,212751,308236,495764,506
Benoni50,000164,000166,649576,587172,809586,842178,533597,458
Boksburg90,000268,000146,747477,164151,550484,841156,115492,723
Brakpan20,00075,000107,818360,478112,080367,848116,030375,289
Germiston / Edenvale119,000317,000119,899350,263123,925356,806127,433363,144
Kempton Park59,000178,000454,1551,392,917470,7581,421,749485,2541,449,985
Nigel18,00039,00040,729137,42242,126139,31143,496141,386
Springs40,000126,00074,390245,92776,968249,62279,313253,519
Sub-Total (Towns)435,0001,292,0001,196,2003,858,1471,237,2503,926,6771,272,9013,996,123
Townships & Surrounding Residential Communes
Tembisa160,000533,000
Vosloorus44,000170,000
Katlehong120,000450,000
Tokoza38,000113,000
Duduza20,00075,000
Tsakane40,000155,000
KwaThema30,000103,000
Daveyton40,000132,000
Etwatwa45,000168,000
Sub-Total (Townships)537,0001,899,000
Informal Settlement Baselines
Informal Settlements Summary125,0002,038,000164,178
Neighbourhoods Overview · 2018/19 (Detailed Town Breakdown)
SettlementHouseholdsPopulation
Alberton36,075121,536
Benoni48,675158,778
Boksburg87,852260,322
Brakpan21,65773,080
Edenvale17,11849,293
Germiston91,275255,864
Kempton Park53,778171,576
Nigel11,51138,319
Springs38,823121,608
Basic Services Access · Master Multi-Year Dashboard
Electricity MSL 2023/24
98.3%
Water MSL 2023/24
99%
Sanitation MSL 2023/24
65.9%
Waste Col. MSL 2023/24
100%
Water Below MSL HHs
11,311
stable 2018–2024
Flush Toilets 2023/24
513,521
HHs
Waste Col. HHs 2022/23
948,227
Bucket Toilets 2023/24
478,819
below MSL

Water MSL · HHs above minimum · 2018/19–2024/25

Source: T 3.1.3 — Water Service Delivery Levels (merged 2022/23–2024/25 reports)

Electricity MSL % · 2019/20–2023/24

Sanitation Type Breakdown · 2023/24 (HHs)

Waste Collection HHs · 2019/20–2023/24

Water Use by Sector · 2022/23–2024/25

Water Use by Sector · cubic meters (3-year trend)

Source: T 3.1.2 — merged from 2022/23, 2023/24, 2024/25 annual reports.
Detailed Municipal Service Delivery Registers
Performance Metrist2009201020112019/202020/212021/222022/232023/24
Electricity Index (%)78.5%76.3%73.8%98.2%98.5%100.0%98.4%98.3%
Water Index (%)93.2%93.5%93.2%99.0%99.0%99.0%99.0%99.0%
Sanitation Index (%)89.2%89.8%89.7%65.9%65.9%65.9%65.9%65.9%
Waste Collection Index (%)93.1%93.7%93.6%100.0%100.0%100.0%100.0%100.0%
2024/25 column verified against source (2024/25 AR, T 3.1.3): total households evaluated jumps from 1,032,199 (2023/24) to 1,421,003 (2024/25), a ~38% one-year increase across every category uniformly — this is in the City's own report as published, not an extraction error, but it doesn't reconcile with any organic household growth trend and is flagged here for caution.
Water Network Subcategory2009/102010/112011/122018/192019/202020/212021/222022/232023/242024/25
Piped water inside dwelling445,477479,726353,996510,858513,175509,658510,598512,844514,3071,132,199
Piped water inside yard203,624381,762381,762381,762382,736382,866384,329182,198
Public tap (within 200m)155,156153,778119,417119,217119,317119,537119,667119,77748,434
Other supply (within 200m)2,2112,2112,2112,2352,3652,4759,040
≥ Min. Service Level sub-total606,623634,882711,3981,012,0371,016,3651,012,9481,015,6161,018,7421,020,8881,371,871
≥ Min. Service Level %100%100%98%99%99%99%99%99%99%
Other supply (more than 200m)11,31111,31111,31111,31111,31111,311
< Min. Service Level sub-total11,31111,31111,31111,31111,31111,311
Total Households Evaluated1,023,3481,027,6761,024,2591,026,4171,029,0531,032,199
Sanitation Facility Classification2018/192019/202020/212021/222022/232023/24
Flush toilet (connected to sewerage)508,458509,658510,858512,058512,058513,521
Flush toilet (with septic tank)3,4293,4293,4293,4293,4293,429
Chemical toilet217,245217,245217,245217,245218,282218,506
Pit toilet (ventilated)80,61380,61380,61380,61380,61380,613
Other toilet (above MSL)179,824179,824179,824179,824179,824179,824
≥ Min. Service Level sub-total989,569990,769991,969993,169994,206995,893
≥ Min. Service Level %65.9%65.9%65.9%65.9%65.9%65.9%
Bucket toilet477,682477,682477,682477,682478,719478,819
Other toilet (below MSL)23,59423,59423,59423,59423,59423,594
No toilet provisions11,80611,80611,80611,80611,80611,806
< Min. Service Level sub-total513,082513,082513,082513,082514,119514,219
Total Households Evaluated1,502,6511,503,8511,505,0511,506,2511,508,3251,510,112
Energy Matrix Distribution Parameters2019/202020/212021/222022/232023/24
Electricity (conventional connection ≥ MSL)82,76976,68466,87756,26450,424
Electricity — prepaid meters (≥ MSL)505,210580,852527,617544,954543,987
≥ Min. Service Level sub-total587,979657,536594,494601,218594,411
≥ Min. Service Level %98.2%98.5%100.0%98.4%98.3%
Other energy sources (below MSL)10,88610,015010,00010,003
< Min. Service Level %1.8%1.5%0.0%1.6%1.7%
Total Households Evaluated598,865667,551594,494611,218604,414
Solid Waste Collection Trackers2019/202020/212021/222022/232023/24
Removed at least once a week (Regular Kerbside)883,254888,589883,890948,227961,000
≥ Min. Service Level sub-total883,254888,589883,890948,227961,000
≥ Min. Service Level %100%100%100%100%100%
< Min. Service Level sub-total00000
Financial Overview · Master Dashboard
Total Revenue 2024/25
R52.95bn
from R27.5bn 2015/16
Total Expenditure 2024/25
R55.83bn
Net Deficit 2024/25
-R2.88bn
Capex 2022/23 Actual
R2.94bn
Employee Cost %
21.0%
of expenditure, 2022/23
Repairs & Maint %
5.07%
Finance Charges %
2.37%
Capex Budget Spend %
91.1%
vs original budget
Total Revenue vs Expenditure · Master Time Series (2015/16–2024/25, latest restated)

Total Revenue vs Total Expenditure · R billion, excl. capital transfers

Each year uses the latest restated actual figure (e.g. 2023/24 uses the 2024/25 AR's restatement of R50.02bn/R51.92bn, not the 2023/24 AR's own R51.33bn/R50.68bn). The municipality has run an operating deficit (before capital transfers) in every year of this series bar 2015/16. The 2022/23 Expenditure restatement (2023/24 AR: R49.65bn vs the 2022/23 AR's own R46.32bn actual, +7.2%) is the largest single-year revision but not extreme enough to flag as an anomaly the way the GVA figures were.

Revenue vs Expenditure · 2022/23 (R thousand)

Capital Expenditure · 2009/10–2022/23 (R thousand)

Financial Summary · 2017/18
Description2016/17 Actual2017/18 Orig Budget2017/18 Adj Budget2017/18 ActualVariance %
Capital expenditure4,702,0356,399,3576,361,9525,636,617-13.53%
Transfers recognised — capital1,788,4572,304,6642,288,7232,001,283-15.16%
Borrowing1,300,0003,245,4273,180,255
Internally generated funds1,613,578849,265892,9753,635,335+76.64%
Total current assets12,158,52714,422,97318,688,61911,841,275-21.80%
Total non-current assets51,586,26055,301,65457,535,96155,225,128-0.14%
Total current liabilities8,527,8198,988,7109,126,4899,730,516+7.62%
Total non-current liabilities7,642,02911,826,36413,024,6838,297,897-42.52%
Community Wealth / Equity47,574,94048,909,55354,073,40849,037,989+0.26%
Net cash from operating activities3,075,2194,725,6137,134,4762,965,956-59.33%
Net cash from investing activities-4,930,426-6,219,561-7,059,857-6,235,704+0.26%
Net cash from financing activities-307,4262,569,3172,867,728987,588-160.16%
Cash / cash equivalents at year end5,809,9549,364,21313,408,0643,527,794-165.44%
Grant2016/17 Actual2017/18 Orig Budget2017/18 Adj Budget2017/18 ActualVariance %
National Government (total)3,076,3823,339,3393,489,8423,218,171-3.77%
— Equitable Share2,381,3672,719,8612,719,8612,719,8610%
— Finance Management1,0501,0501,0501,042-1%
— EPWP Operational22,12344,71844,71844,6230%
— USDG Operational & Other663,906533,710604,213333,430-60%
Provincial Government (total)343,859373,052385,118348,624-7.01%
— Health Subsidy124,133130,340130,340130,3400%
— Ambulance Subsidy150,624158,155158,155158,1550%
— SETA9,02525,13225,13210,797-133%
— Housing34,80541,20351,20331,204-32%
Total Operating Transfers & Grants3,420,2413,712,3913,874,9593,566,796-4.08%
Revenue Source2016/17 Actual2017/18 Orig Budget2017/18 Adj Budget2017/18 ActualVariance vs OrigVariance vs Adj
Property rates3,946,6594,661,2844,661,2845,200,065+10.36%+10.36%
Service Charges — electricity11,824,17013,458,63713,458,63712,808,618-15.18%-13.86%
Service Charges — water3,217,1674,260,8894,212,3043,699,417-41.05%-45.21%
Service Charges — sanitation1,054,6681,646,2741,694,8601,167,181-25.07%-25.07%
Service Charges — refuse961,4471,486,7091,486,7091,188,710-106.35%-61.09%
Interest earned — external investments632,624322,080322,080613,811-23.49%-23.49%
Fines319,360274,237289,237391,954-251.72%-251.72%
Agency services276,375304,932304,932293,199+33.43%+33.22%
Transfers recognised — operational4,464,9723,502,4183,513,2785,261,059-86.28%-86.28%
Total Revenue (excl. capital transfers)27,501,10132,378,96932,374,95132,019,096-1.12%-1.11%
GrantBudgetAdj BudgetActualVariance vs BudgetVariance vs Adj Budget
Integrated National Electrification Programme40,00040,00039,8550%0%
Public Transport Network Grant660,718580,718346,563-91%-68%
Energy Efficiency & Demand-side Management12,00012,00012,0000%0%
Neighbourhood Development Programme Grant82,000102,57496,426+15%-6%
Expanded Public Works Programme44,71844,71844,6230%0%
Financial Management Grant1,0501,0501,0500%0%
SETA25,13225,13210,797-133%-133%
HIV/AIDS12,83013,23713,237+3%0%
HSDG (Human Settlements Dev. Grant)41,20351,20331,204-32%-64%
Total982,097933,978657,986-49%-42%
Statement of Financial Performance · Longitudinal Sheets
Financial Parameter (R'000) 2011/12 2014/15 2015/16 2016/17 2022/23
Adj. BudgetActual Adj. BudgetActual Adj. BudgetActual Adj. BudgetActual Orig. BudgetAdj. BudgetActual
Revenue Categories
Grants & Operational Transfers4,551,7604,557,5404,464,9725,139,1505,047,6407,878,4597,849,8727,628,681
Taxes, Levies, Rates & Service Charges15,816,53015,438,40221,077,11425,620,55122,863,68337,442,89538,794,70436,804,009
Other Own Revenue / Investment Revenue723,748808,8021,959,0151,615,2491,688,3903,766,1534,487,1934,855,184
Total Operational Revenue21,092,03820,804,74428,082,97327,395,47931,712,16729,648,25934,172,63631,388,17049,087,50751,131,76949,287,875
Expenditure & Outcomes
Less: Operational Expenditure20,849,85220,239,47226,542,96925,123,94128,928,51127,478,01132,358,17730,136,20146,566,95948,706,94046,319,268
Net Surplus / (Deficit)242,186703,6651,540,0042,271,5382,783,6572,170,2481,814,4591,251,9692,520,5492,424,8302,968,607
Performance Track Indicator2011/122014/152015/162016/172020/212021/222022/23
Employee Cost %19.96%21.0%
Repairs & Maintenance %8.44%5.07%
Finance Charges & Impairment %2.20%2.37%
Capex Original Budget (R'000)2,374,7852,650,7082,980,9333,790,3664,719,5493,883,6113,230,981
Capex Adjustment Budget (R'000)2,252,1042,557,7392,987,4193,810,9504,514,5413,075,5323,030,037
Capex Actual (R'000)2,001,0142,370,4372,612,3013,069,1644,476,9083,038,4912,942,669
% Capex Spent (vs Orig Budget)89.4%87.6%81.0%94.9%78.2%91.1%
% Capex Spent (vs Adj Budget)92.7%87.4%80.5%99.2%98.8%97.1%
Source: Annual Reports 2011/12–2022/23 — Financial Performance chapters
Financial Competency · 2011/12
DescriptionTotal officials employed by municipal entitiesTotal Consolidated: AConsolidated: Total of A and BTotal officials employed by municipalityTotal officials that meet prescribed competency levelsTotal Competency assessments completed
Accounting officer134300
Chief financial officer134300
Senior managers2724512800
Any other financial officials44144139101
Heads of supply chain management units101100
Supply chain management senior managers1121400
TOTAL4723150344001
Details2011/2012 Actual R'0002012/2013 Original Budget R'0002012/2013 Adjustment Budget R'0002012/2013 Actual R'000Variance to Budget %
Total Operational Revenue26,030116,84923,30428,062-316%
Employees73,41362,84563,59185,27426%
Repairs and Maintenance3,46695,43383,73750,886-88%
Other2,2848,4699,6017,042-20%
Total Operational Expenditure79,163166,747156,928143,201-16%
Net Operational Expenditure53,13349,898133,624115,13957%
Details2011/2012 Actual R'0002012/2013 Original Budget R'0002012/2013 Adjustment Budget R'0002012/2013 Actual R'000Variance to Budget %
Total Operational Revenue
Employees1,3341,2381,2651,2632%
Repairs and Maintenance
Other7,3128,05228,3765,019-60%
Total Operational Expenditure8,6469,29029,6406,282-48%
Net Operational Expenditure8,6469,29029,6406,282-48%
Details2011/2012 Actual R'0002012/2013 Original Budget R'0002012/2013 Adjustment Budget R'0002012/2013 Actual R'000Variance to Budget %
Total Operational Revenue1221-71%
Employees23,89925,83725,83723,416-10%
Repairs and Maintenance3210316816236%
Other17,68019,68622,82818,221-8%
Total Operational Expenditure41,61145,62648,83341,799-9%
Net Operational Expenditure41,61045,62448,83141,798-9%
Details2013/2014 Actual (R'000)2014/2015 Original Budget (R'000)2014/2015 Adjustment Budget (R'000)2014/2015 Actual (R'000)2014/2015 Variance to Budget (%)
Total Operational Revenue33,41280,80282,57681,5431%
Employees128,888148,279155,824140,941-5%
Repairs and Maintenance12,22022,97122,95622,575-2%
Other18,62866,93975,16571,5896%
Total Operational Expenditure159,736238,189253,946235,105-1%
Net Operational Expenditure126,325157,386171,370153,561-2%
Details2013/2014 Actual (R'000)2014/2015 Original Budget (R'000)2014/2015 Adjustment Budget (R'000)2014/2015 Actual (R'000)2014/2015 Variance to Budget
Total Operational Revenue549,702298,050301,383202,032-48%
Employees40,10158,70254,20446,558-26%
Repairs and Maintenance401,989492,534488,807317,666-55%
Other860,025942,778942,149825,479-14%
Total Operational Expenditure1,302,1151,494,0141,485,1601,189,704-26%
Net Operational Expenditure752,4131,195,9641,183,777987,672-21%
Finance Department · Capital Expenditure Portfolio (2011/12 Era)
Original Capex Budget
R179.0m
Adjusted Capex Budget
R142.3m
Actual Capex Spending
R75.8m
Financial year closing
Capex Net Variance
-136%
vs original budget
Langaville Electrification
R26.5m
Renewable Energy Grid
R10.0m
Smart Water Metering
R7.5m
Revenue Enhancement
R130.0m
0% deployment spend
Capital ProjectOriginal BudgetAdjustment BudgetActual ExpenditureVariance vs Original %Total Project Value
Total Consolidated Financial Capital Portfolio179,025142,34475,777-136%
Ad Hoc Allocation1,0000%2,069
Business Intelligence System7,0000%
Business Process Re-Engineering (BPR) Core Engine15,0008,0007,975-88%7,975
CPO / Central Germiston Supply Chain Stores8,0005,2004,379-83%20,879
Credit Control and Debt Management System7,0000%
Customer Care Revenue Call Centre Telephony6,0005,056100%5,056
ICT Equipment2,0000%
ICT Equipment (2)2,1601,2791,001-116%14,026
Implementation of Waste to Energy projects10,0000%
Langaville Grid Electricity Network Restitution Project26,47926,479100%26,479
Core Meter Management System Control Node7,5006,696100%6,696
Administrative Office Furniture & Ergonomics735735722-2%3,853
Operational Buildings - Airconditioners290290100%290
Operational Buildings - Security Control203203100%203
Other Equipment5030100%2,427
Paving Open Spaces: K/Park & Alberton Distribution Logistics530721721+27%721
Payment Receipting System5,0000%
Credit Control Procurement Equipment (System Cut-offs)6,0003,007994-503%994
Renewable Energy Alternatives Sub-Programme10,0009,953100%9,953
Municipal Customer Paypoints Renovation & Structural Overhaul3,0003,0002,928-2%2,928
Strategic Revenue Enhancement Framework Projects130,0000%
Water Intelligent Automated AMR Meters Rollout50,0007,471100%7,471
Directorate Operational & Enforcement Vehicles600880877+32%8,887
Source: Annual Report 2011/12 — Chapter 3.25 Financial Services
Economic Activity & Sectoral GVA · Multi-Year Trend
Total GVA 2021
R364bn
Total GVA 2022
R393bn
Total GVA 2023
R418bn
GVA Growth 2021–23
+14.7%
Largest Sector
Finance
R113.8bn (2023)
Manufacturing (2023)
R99.6bn
Community Services (2023)
R70.0bn
Mining (2023)
R9.3bn
declining

Gross Value Added (GVA) by Sector · 2021–2023 (R million, current prices)

Source: Annual Report 2023/24 — Economic Activity by Sector

GVA Sector Composition · 2023 (%)

Finance, Manufacturing & Trade GVA · 2021–2023 (top 3 sectors)

GVA & Employment by Sector · 2015–2017

Gross Value Added by Sector · 2015–2017 (R million)

Employment by Sector · 2015–2017 (Persons)

Sector2015 (R'000)2016 (R'000)2017 (R'000)
Agriculture982,4171,127,4181,297,682
Mining5,111,1465,995,5406,565,610
Manufacturing52,229,37156,315,16058,977,378
Electricity8,796,6019,429,8059,967,836
Construction10,498,57711,318,00512,351,496
Trade33,174,22635,725,16839,266,745
Transport30,208,56731,630,37733,668,922
Finance51,554,82256,499,04960,823,265
Community Services53,372,46258,436,36463,661,662
Total Industries245,928,188266,476,885286,580,597
Taxes less Subsidies on products32,988,18636,858,71537,810,075
Total GDP278,916,375303,335,600324,390,673
Sector201520162017
Agriculture10,0158,9269,676
Mining7,3578,1028,076
Manufacturing149,808147,101149,639
Electricity5,9635,7415,924
Construction73,83176,76378,799
Trade253,651254,177261,693
Transport84,34984,04686,188
Finance289,435288,235294,398
Community Services219,369223,138224,762
Total1,093,7781,096,2291,119,156
Detail2015/162016/172017/18
Number of EPWP projects3218079
Jobs created through EPWP9,79310,9832,158
Indicator2016/17 Target2016/17 Actual2017/18 Target2017/18 Actual2018/19 Target
Enterprises in business incubation programme262265200205400
People benefiting from skills development programmes2,5002,1371,5001,5061,500
Aerotropolis projects facilitated12110
Investment attracted (R-value)R7bnR7.3bnR4bnR4.059bnR5bn
Business tourists visiting Ekurhuleni39,460133,82943,406133,92343,406
2019/20–2021/22 use the 2022/23 AR's restated figures, which run ~35–40% below every adjacent year — see Data Quality note on the Overview tab. Used per the "latest restated" rule but flagged as likely a source-data error, not a genuine correction.
Sector Category2011/122012/132013/142014/152015201620172017/182018/192019/202020/212021/22202120222023
Agriculture, Forestry & Fishing0.690.710.730.840.981.131.301.271.180.380.370.371.952.272.31
Mining & Quarrying5.355.725.775.725.116.006.576.756.583.924.184.549.409.699.33
Manufacturing Industries48.1950.3254.6359.0652.2356.3258.9860.2161.5541.3939.4342.8282.2591.4599.63
Electricity, Gas & Water Distribution6.538.048.709.298.809.439.9711.7812.523.933.864.0214.1515.7217.37
Construction Assets & Infrastructure7.938.838.619.4710.5011.3212.3511.8712.558.527.437.6710.0710.4610.97
Wholesale & Retail Trade, Catering & Accommodation29.9031.7832.9435.4833.1735.7339.2738.6841.0332.1531.0435.2548.8852.4956.85
Transport, Storage & Communication Infrastructure22.6925.4827.5128.9930.2131.6333.6733.6435.1624.7222.3823.4030.7934.8337.42
Finance, Real Estate & Business Services40.8044.0946.0548.2551.5556.5060.8257.7860.0141.8339.2039.33102.93108.93113.83
General Government & Community Services53.3758.4463.6662.3466.7869.5670.1473.5163.8567.0670.04
Total Local Industries (GVA at Current Prices)245.93266.48286.58320.95338.25226.30218.04230.92364.26392.92417.76
Source: Annual Reports 2017/18 & 2023/24 — Economic Activity by Sector
Infrastructure Network Asset Inventory · Master Sheet
Total Baseline Households
1.08m
2015/16 Benchmark
Formal Dwelling Ratio
77.3%
2015/16 calculation
Total Tarred Roads 2015/16
8,085km
Total Gravel Roads 2015/16
1,200km
Household Infrastructure Baselines · Historical 3-Year Tracking
Dwelling Structural Type2013/142014/152015/16
Very Formal (Brick/Concrete structural dwellings)508,515526,639542,964
Formal (Standard residential units)271,586281,579295,394
Informal (Unstructured temporary settlements)225,957227,955231,183
Traditional (Earthen/Organic building materials)1,6291,7502,149
Other dwelling alternative matrix types12,48012,90112,672
Total Housing Assets Tracked1,020,1661,050,8251,084,363
Sanitation Technology Type2013/142014/152015/16
Flush toilet network infrastructure902,129934,959971,046
Ventilation Improved Pit (VIP Infrastructure)7,4987,8498,605
Standard Pit toilet configurations63,06563,68263,136
Bucket collection layout systems10,29411,58313,588
No documented structural containment provisions37,18032,75227,989
Total Households Evaluated1,020,1661,050,8251,084,363
Water Connection Proximity Category2013/142014/152015/16
Piped water inside internal dwelling structure582,777606,714631,810
Piped water boundary layout inside yard limits299,132304,849312,677
Communal public terminal standpipes ≤200m (RDP Met)77,41677,92977,933
Communal public terminal standpipes >200m (Below RDP)34,57333,12932,078
No access to structured municipal piped grid system26,26928,20529,864
Total Households Evaluated1,020,1661,050,8251,084,363
Employment Dynamics & Labor Market Trends
Unemployment 2024/25
36.3%
Low-skilled Emp 2024/25
17.9%
Formal Sector (Baseline)
759,252
2010 tracking
Informal Sector (Baseline)
93,013
2010 tracking

Longitudinal Unemployment Rate Trend · 2009–2025 (%)

Employment Chart Breakdown by Main Industry Sector

DepartmentApproved PostsEmployeesVacanciesVacancy %
City Planning2792748624%
Communication & Brand Management45501725%
Corporate Legal Services2972919525%
Customer Relations Management400399287%
DEMS (Disaster & Emergency)1,4361,4421278%
Economic Development75753029%
EMPD (Metro Police)2,5132,74636312%
Energy98497319617%
Finance99998430223%
Fleet Management1761997327%
Health & Social Development1,7021,8021578%
Human Resources1941928330%
Human Settlement2062256121%
ICT1331265731%
Roads & Storm Water79279717618%
SRAC1,2641,28423315%
Transport72973518020%
Waste Management1,4701,42025715%
Water & Sanitation96296627722%
Totals16,84017,1253,36716%
YearAppointments at StartTerminationsTurnover Rate
2015/1616,2674092.51%
2016/1717,0827604.45%
2017/1817,4226213.56%
Source: Annual Report 2018/19 — Employment & HR tables
Human Settlements & Housing Backlog Metrics
Housing Backlog 2022/23
20.0%
Housing Backlog 2023/24
20.7%
Housing Backlog 2024/25
20.2%
Formal Settlements Ratio
77.0%
2017/18

Housing Delivery Backlog Tracking Index · 2022/23–2024/25

YearTotal HouseholdsHouseholds in Formal Settlements% in Formal Settlements
2014/151,092,585755,69969.2%
2015/161,066,248768,41672.1%
2016/171,040,547775,81274.6%
2017/181,015,465781,95177.0%
Service Objective2017/18 Target2017/18 Actual2018/19 Target2018/19 Actual
Subsidised housing provided689328689820
Social housing provided2562568991,287
Serviced stands4,5513,4354,5517,436
Hectares of land acquired120253.8ha120120
Detail2016/17 Actual2017/18 Orig Budget2017/18 Adj Budget2017/18 ActualVariance
Total Operational Revenue812,8381,195,2071,173,5151,111,032-8%
Employees83,789108,790107,93299,862-9%
Repairs and Maintenance52,639116,008138,019131,359+12%
Other1,100,513480,713484,115736,221+35%
Total Operational Expenditure1,236,940705,512730,066967,441+27%
Net Operating Surplus/(Deficit)-424,102-489,695-443,449-143,591-241%
ProjectAdj BudgetActual BudgetActual ExpenditureVariance
Total All1,001,526984,880919,415-9%
Alliance Extension 177,25979,82379,849+3%
Alliance Extension 924,94320,84320,248-23%
Apex Ext 1222,32721,63621,480-4%
Balmoral Extension 455,98028,16228,162-99%
Chief A Luthuli Park Ext 6 (Benoni)42,04041,875100%
Remaining projects genuinely truncated in the source PDF (2017/18 AR, Table 59) — the table cuts off after 6 of an unknown number of projects, with the listed rows summing to only ~23% of the stated Total All (R1,001,526k); verified this isn't an extraction gap by checking the surrounding pages, which move on to a different table. Not recoverable from this source.
Fiscal YearTotal Backlog Households CheckedHouseholds in Formalized SettlementsProportional Share in Formal Settlements
2012/13726,641582,33680.1%
2013/14707,391563,08679.6%
2014/15691,793547,48879.1%
2015/16684,305540,30579.0%
The 2015/16 AR labels these years relative to its own reporting year ("year-0" = 2015/16) rather than giving absolute years — resolved here from the report's own year context, not renamed arbitrarily.
Source: Annual Reports 2015/16–2017/18 — Human Settlements chapters
Sports, Recreation, Arts & Culture · Directorate Framework
Dept / Directorate
Sport & Rec
Net Operational Outlay 2017/18
R835m
Capex Actual 2017/18
R123m
Capex Actual 2015/16
R189m
Reporting PeriodActual Registered BasePlanned Target Baseline
Quarter 1 (Q1)7,0008,273
Quarter 2 (Q2)8,0008,701
Quarter 3 (Q3)19,00052,466
Quarter 4 (Q4)18,00050,477
Annual Consolidated Total50,00050,477
Detail2016/17 Actual2017/18 Orig Budget2017/18 Adj Budget2017/18 ActualVariance
Total Operational Revenue31,66522,99623,67920,758-11%
Employees387,224452,984431,300427,914-6%
Repairs and Maintenance36,65437,25234,20430,669-21%
Other389,561165,104170,246396,840+58%
Total Operational Expenditure813,439655,340635,749855,423+23%
Net Operational Expenditure781,774632,344612,070834,664+24%
Full itemized list recovered from the 2018/19 AR's repeat of this table (58 projects, vs. 9 previously captured). The itemized rows sum to ~R105.0m/R108.7m/R104.6m — about 21% below the "Total All" line as reported in both source appearances; this gap exists in the source itself (likely unlisted rounding/consolidation items) and hasn't been forced to reconcile.
ProjectBudgetAdj BudgetActualVariance
Total All (as reported)132,900128,990123,096-8%
Actonville Tennis (Benoni)750750100%
Alberton Korfball: Resurface courts1700%
Alberton Ringtennis: Resurface courts1700%
Atlasville Tennis Club: Resurface courts170123123-38%
Benoni Northerns Tennis Club: Resurface courts17024324330%
Birch Acres Tennis Club: Resurface courts170161161-5%
Brakpan Netball Club: Resurface courts170106106-61%
Construct OR Tambo Statue13,9006,0506,050-130%
Construction: New Swimming Pool — Duduza15,00011,00010,994-36%
Construction: New Swimming Pool — Eden Park5,00012,60212,22359%
Construction: New Library — Etwatwa6,0001,488957-527%
Duduza Gym Hall: Resurface courts17031631646%
Essenwood Basketball Club: Resurface courts1707171-138%
Fencing Benoni Northerns3,00017099-2932%
Furniture & Equipment: Arts & Culture1,0001,3301,33025%
Furniture: Community and Sport Centres1,000964755-32%
ICT Equipment2,0002,0001,9960%
Kempton Park Ringball Club: Resurface courts17030730745%
Kempton Park Tennis Club: Resurface courts17020520517%
Libraries Furniture1,0002,0001,78544%
Libraries ICT Equipment (1)1,0001,000987-1%
Libraries ICT Equipment (2)1,0002,5992,59561%
Modular Library — Vosloorus0%
Modular Library — Birch Acres0%
Ncala Court: Resurface courts17023123126%
Office Furniture1,000618546-83%
Pine Grove Tennis Club: Resurface courts170117117-45%
Recapitalisation of Libraries — Refurbish HP Mokoka Library (Daveyton)21287100%
Recapitalisation of Libraries — Refurbish Jerry Moloi Library (Etwatwa)240201100%
Recapitalisation of Libraries — Refurbishment Eden Park Library5000%
Recapitalisation of Libraries — Refurbishment Edenvale Library2,0004,3434,34354%
Recapitalisation of Libraries — Refurbishment Nigel Library139124100%
Refurbish Arthur Ashe Tennis Courts3,0002,953100%
Refurbish Katlehong Stadium2,0001,8721,285-56%
Refurbishment of Chris Hani Sport Park1,7191,719100%
Rehabilitation Brackenhurst Library3,0003,2633,1404%
Rehabilitation of Isaac Mokoena Library2,0001,5671,475-36%
Rehabilitation Phomolong Library1,5001,5001,5000%
Rehabilitation Springs Library2,0005,4005,19962%
Resurface Rondebult Tennis Courts484480100%
Riverridge Tennis Club: Resurface courts1700%
Sam Ntuli Stadium: Resurface courts17023123126%
Specialized Equipment3,0003,3993,2277%
Specialized Equipment — OR Tambo Library4,000401278-1337%
Springs Ringball Club: Resurface courts11030730764%
Thokoza Youth Centre Tennis Court: Resurface courts17048748765%
Tswelopele Multipurpose Courts: Resurface courts1701791795%
Upgrade Bedfordview Hall50089882039%
Upgrade Boksburg Athletics Track6,5006,5606,143-6%
Upgrade Boksburg Library3,0005,0064,93739%
Upgrade Coen Scholtz Art Centre750891699-7%
Upgrade Daveyton Swimming Pool9,50012,70612,70625%
Upgrade DH Williams Hall5001,7631,76372%
Upgrade Kempton Park Library3,0003,0003,0000%
Upgrade Kempton Park Swimming Pool500500312-60%
Upgrade Kwa Thema Sport Park1,0001,0009960%
Upgrade Mehlareng Stadium1,0001,4421,32525%
Upgrade Olympia Park Swimming Pool5,0001,6931,693-195%
Project Infrastructure DesignationOriginal BudgetAdjusted BudgetActual Capex ExpenditureVariance vs Adj %
Total Consolidated Capital Portfolio193,400200,282189,261-2%
Benoni North Swimming Pool Rehabilitation500576529+5%
Construction: New Swimming Pool — Eden Park Regional15,00015,00015,0000%
Construction: New Library Facility — Tsakane Grid9,00014,2769,643+7%
Germiston Theatre Civic Complex Construction35,00029,00027,411-28%
Re-mobilise — 60 Eco Gyms Green Deployment8,0008,5028,502+6%
Re-mobilise — Refurbishment of 50 Community Facilities50,00050,00050,0000%
Upgrade Tembisa Regional Library Infrastructure8,0007,2347,234-11%
Operational Utility Vehicles Procurement10,00010,80810,774+7%
Source: Annual Reports 2015/16 & 2017/18 — SRAC chapters
Community Safety, Disaster & Emergency Management
Dept / Directorate
Comm. Safety
DEMS Total Posts 2014/15
1,534
DEMS Vacancy Rate 2014/15
10%
Operational Ambulances 2014
60
Paramedics 2014
293
Fire Incidents (Informal Settlements)
45
down from 230 baseline
Risk & Disaster Management · 2011/12 Baseline
Job Level2010/11 EmployeesPosts2011/12 EmployeesVacancies (fulltime equivalents)Vacancies (% of total posts)
0 - 30%
4 - 610%
7 - 90%
10 - 120%
13 - 150%
16 - 180%
Section 5751480%
Total151480%
Fire, Ambulance & Disaster Services · 2012–2015
Service IndicatorsYear -1 TargetYear -1 ActualYear 0 TargetYear 0 ActualYear 1 TargetYear 3 Target
Number of functional Disaster & Emergency Management facilities111110
Reduction of Fire incidents reported in informal settlements300230230455230
% compliance with SA National Standard 10090 (speed of response)82%82%82%82%86%85%
Details2012 Estimate2012 Actual2013 Estimate2013 Actual2014 Estimate2014 Actual
Patients taken to medical facilities during the year112,826113,296161,629170,000
Avg time: call to arrival at patient (urban)15 min15 min13 min15 min
Avg time: call to arrival at patient (rural)n/an/an/an/a
No. ambulances60606160
No. paramedics240240293293
Service IndicatorsYear -1 TargetYear -1 ActualYear 0 TargetYear 0 ActualYear 1 TargetYear 3 Target
Number of Operational Ambulances on 24/7506666605860
% reduction of Emergency Medical calls not serviced0001%1.16%1%
Job Level2013/2014 Employees2013/2014 Posts2014/2015 Employees2014/2015 Vacancies2014/2015 Vacancies %
0 - 3364233%
4 - 6191281131512%
7 - 95131,1131,032817%
10 - 121792221784420%
13 - 158284637920%
16 - 1885119218%
Section 5778800%
Total1,6341,5341,38115310%

Metro Police (EMPD) — Financial Performance · 2022/23–2024/25 (R'000, latest restated)

Detail2022/23 Actual2023/24 Actual2024/25 Orig Budget2024/25 Adj Budget2024/25 Actual
Total Operational Revenue983,499982,6841,155,5761,178,245536,685
Employees2,177,8042,412,9942,518,5522,400,1212,388,311
Repairs and Maintenance144272,0232,023667
Other1,011,0951,333,3361,257,3801,364,380953,374
Total Operational Expenditure3,189,0443,746,3573,777,9563,766,5243,342,353
Net Operating Deficit-2,205,545-2,763,673-2,622,380-2,588,279-2,805,668
2023/24 uses the 2024/25 AR's restatement (Expenditure R3.75bn), which runs ~5.8% above the 2023/24 AR's own actual (R3.54bn) — used per the latest-restated rule. 2024/25 Revenue collapses to R536.7m against an adjustment budget of R1.18bn (-54% variance) — verified as reported, not an extraction error, but a sharp one-year drop worth flagging.

EMPD Staffing · 2023/24→2024/25

Job Level2023/24 Posts2024/25 Posts2024/25 EmployeesVacanciesVacancy %
0–32035211440%
4–61,4831,6531,45419912%
7–91,7501,9751,72325213%
10–1234347735612125%
13–1575101752626%
16–182339281128%
19–20121150%
Total3,6954,2823,65862415%

Capital Expenditure · 2024/25 (R'000)

ProjectBudgetAdj BudgetActualVariance
Total All30,00040,00039,988+33%
Vehicles15,00025,00024,988+67%
Establish MVRA/DLTC Katlehong15,00015,00015,0000%

By-law Enforcement

2023/24: 120 planned by-law enforcement policing operations targeted, 163 achieved — overachievement attributed to intensified operations in response to by-law contraventions (2023/24 AR performance scorecard, EMP1).

CCTV/surveillance infrastructure: no dedicated financial or asset table found across any of the 13 available Annual Reports — this appears to be a genuine reporting gap in the source, not an extraction omission.
Source: Annual Reports 2011/12 & 2014/15 — Risk Management, Fire, Ambulance & DEMS chapters
Human Settlement · Historical Baseline Ledger (2011/12 Era)
Total Posts 2011/12
258
Active Headcount
208
2011/12 actual
Organogram Vacancies
50 (19%)
Capex Spend 2011/12
R53.7m
Operational Revenue
R95.2m
Operational Expenditure
R289.2m
Net Fiscal Deficit Outlay
R194.0m
Housing Backlog 2024/25
20.2%

Financial Performance Matrix · Human Settlement 2010/11 vs 2011/12 (R'000)

Staff Establishment Profiles · Human Settlement 2010/11 vs 2011/12

Financial Component Detail2010/11 Actual2011/12 Orig Budget2011/12 Adj Budget2011/12 ActualVariance vs Adj %
Total Departmental Operational Revenue164,10144,98874,32295,167+53%
Employee Compensation Costs54,43667,15865,37060,979-10%
Asset Repairs & Infrastructure Maintenance14,87215,88715,31312,205-30%
Other Contracted Operational Overheads383,457273,394276,046215,991-27%
Total Departmental Operational Expenditure452,765356,439356,729289,175-23%
Net Fiscal Operational Expenditure Outlay288,664311,451282,407194,008-61%
Job Level Grade RangeApproved Posts 2010/11Active Headcount 2010/11Approved Posts 2011/12Active Headcount 2011/12Vacant Node PositionsCalculated Vacancy %
Task Grades 0–3 (Operational Base Support)111100%
Task Grades 4–6 (Administrative/Clerical)29192922724%
Task Grades 7–9 (Technical Specialists)1771761165%
Task Grades 10–12 (Supervisory & Section Heads)78667869912%
Task Grades 13–15 (Middle Portfolio Managers)21142116524%
Task Grades 16–18 (Senior Advisory & Leadership Nodes)112105112941816%
Total Integrated Organogram Grid2582122582085019%
Source: Annual Report 2011/12 — Chapter 3.5 Human Settlement Performance Review
Local Economic Development (LED) · Strategic Framework
Total Posts 2011/12
28
Active Headcount
23
Organogram Vacancies
5 (17.8%)
Capex Spend 2011/12
R2.9m
Operational Revenue
R1.5m
Operational Expenditure
R26.4m
Net Fiscal Deficit Outlay
R24.9m
Unemployment 2024/25
36.3%

Financial Performance Overview · Local Economic Development (R'000)

Staff Establishment Profiles · LED 2010/11 vs 2011/12

Financial Component Detail2010/11 Actual2011/12 Orig Budget2011/12 Adj Budget2011/12 ActualVariance vs Adj %
Total Departmental Operational Revenue265011,0471,515-86%
Employee Compensation Costs8,33512,71311,3139,908-12%
Asset Repairs & Infrastructure Maintenance1830139-31%
Other Contracted Operational Overheads34,13618,48516,14116,511+2%
Total Departmental Operational Expenditure42,48931,22827,46726,428-4%
Net Fiscal Operational Expenditure Outlay42,46331,17816,42024,913+52%
Detail2016/17 Actual2017/18 Orig Budget2017/18 Adj Budget2017/18 ActualVariance
Total Operational Revenue36,40967,99167,99166,531-2%
Employees141,171102,187152,247151,417+33%
Repairs and Maintenance6,1694,8944,6443,620-35%
Other148,567139,038147,118145,962+5%
Total Operational Expenditure295,907246,120304,009300,999+18%
Net Operational Expenditure259,499178,129236,019234,468+24%
ProjectAdj BudgetActual BudgetActual ExpenditureVariance
Total All145,100145,100142,631-2%
Aerotropolis International Hospitality School3,0007,0006,938+57%
Automotive City — Katlehong, Tembisa, Tsakane10,00015,77715,7770%
Ekurhuleni SMME Innovation Hub10,0003,7193,578-180%
Etwatwa Township Enterprise Hubs24,00018,50018,469-30%
KwaThema Business Hubs30,00030,00029,8810%
Labore & Withoek Industrial Park10,00012,14212,142+18%
Springs Fresh Produce Market Expansion30,00035,62135,621+16%
Environmental Resource Management · 2015/16
Financial Component Summary2014/15 Actual2015/16 Orig Budget2015/16 Adj Budget2015/16 ActualVariance vs Orig Budget
Total Directorate Operational Revenue26153,06345,81941,794-27%
Employee Compensation Costs16,666444,022443,673440,682-1%
Asset Repairs & Infrastructure Maintenance3,54370,59877,85265,299-8%
Other Operational Contracted Overheads32,071149,475152,862174,799+14%
Total Departmental Operational Expenditure52,280664,094674,388680,780+2%
Net Fiscal Operational Expenditure Position52,019611,031628,569638,986+4%
Detail2016/17 Actual2017/18 Orig Budget2017/18 Adj Budget2017/18 ActualVariance
Total Operational Revenue26,49733,76033,77624,425-38%
Employees473,551520,221508,338506,506-3%
Repairs and Maintenance72,47190,59292,83390,2680%
Other185,803139,351139,487141,484+2%
Total Operational Expenditure731,825750,164740,657738,258-2%
Net Operating Surplus / (Deficit)705,328716,405706,881713,8330%
Indicator2016/17 Target2016/17 Actual2017/18 Target2017/18 Actual2018/19 Target
Formal HHs with access to refuse removal674,385674,385682,541682,541689,477
Informal settlements with refuse removal access119119119119
240L bins rolled out88,000100,71388,00077,22860,000
CBD cleanliness levelLevel 3Level 3Level 3Level 2Level 3
IndicatorYr -1 TargetYr -1 ActualYr 0 TargetYr 0 ActualYr 1 Target
PV solar lighting units installed (informal settlements)10,00020,82610,00012,81010,000
Installed capacity of alternative/renewable power2MW2.55MW2MW1MW1.8MW
Number of subsidised households electrified6,0006,0866,0008,9816,000
Unaccounted for electricity (%)11.00%11.39%11.00%12.39%12.00%
Source: Annual Reports 2011/12 & 2015/16 & 2017/18 — LED, Environmental & Energy chapters
Bio-Diversity & Landscape · 2016/17–2019/20
Service ObjectiveService Indicators2016/2017 Target2016/2017 Actual2017/2018 Target2017/2018 Actual2018/2019 Target2019/2020 Target
Increased community compliance with regulatory actions% of targeted members where compliance with environmental legislation100%100%100%100%100%100%
Improved water catchment managementNumber of water bodies with required rehabilitation actions completed445555
Increased access to recreation facilitiesNumber of parks upgraded555555
Job LevelEmployees No.Posts No.Employees (FTE)Vacancies No.Vacancies (% of total posts)
0 - 311100%
4 - 6137814396%
7 - 91157111475%
10 - 122124283%
13 - 1522200%
16 - 18665116.6%
Section 57156373687%
Total191193732010%
Sport, Recreation, Arts & Culture (SRAC) · Arts, Culture & Libraries (2011/12 Era)
Total Posts 2011/12
428
Active Headcount
396
Organogram Vacancies
32 (7%)
Capex Budget 2011/12
R92.1m
Capex Actual Spend
R67.3m
Capex Net Variance
-37%
Operational Expenditure
R127.3m
Employee Cost Baseline
R116.1m
2010/11 tracking

Financial Performance Overview · SRAC 2010/11 vs 2011/12 (R'000)

Staff Establishment Profiles · SRAC 2010/11 vs 2011/12

Project Infrastructure DesignationOriginal BudgetAdjusted BudgetActual Capex SpendVariance vs Orig %
Total Consolidated Capital Portfolio92,08183,60967,283-37%
Chris Hani Memorial Development4,000500374-969%
New Library Facility — Langaville Grid7,00010,84210,840+35%
New Library Facility — Winnie Mandela Node6,0004,0724,026-49%
Germiston Theatre Civic Complex14,0002,1182,061-579%
OR Tambo Precinct Structural Development20,00034,00532,374+38%
Swimming Pools Structural Rehabilitation7,5004,5634,563-64%
Art Centres Community Upgrades300798798+62%
Historical Memorial Sites Construction1,800874874-106%
Job Level Grade RangeActive Headcount 2010/11Approved Posts 2011/12Active Headcount 2011/12Vacant Node Positions (FTE)Calculated Vacancy %
Task Grades 0–3 (Operational Base Support)11100%
Task Grades 4–6 (Administrative/Clerical)15151417%
Task Grades 7–9 (Technical Specialists)22252328%
Task Grades 10–12 (Supervisory & Branch Heads)101105921312%
Task Grades 13–15 (Middle Portfolio Managers)185191181105%
Task Grades 16–18 (Senior Advisory & Leadership Nodes)86918567%
Total Integrated Organogram Grid410428396327%
Source: Annual Report 2011/12 — Tables 41–43 SRAC: Arts, Culture & Libraries
Human Resources & Corporate Services · Institutional Baseline (2011/12 Era)
Employees Trained
3,559
Community Bursaries
162
RPL Attainments
279
HR Approved Posts
260
Active HR Staff
222
Corporate Vacancies
38 (15%)
HR Operational Spend
R117.1m
Skills Dev Expenditure
R30.4m

Corporate Service Statistics · Training Tracks & Learnerships 2011/12

Financial Performance Matrix · Corporate Services 2010/11 vs 2011/12 (R'000)

Active Human Capital Training FrameworkRegistered Beneficiaries
Employee Learnerships: Horticulture & Open Spaces172
Employee Learnerships: Water Reticulation Network Operations130
Community Learnerships: ICT Systems Support Infrastructure99
Community Learnerships: Pharmacist Assistant Clinical Path6
Community Learnerships: Social Auxiliary Support Work15
Community Learnerships: Emergency Medical & Rescue Services195
Experiential Training Placement Allocations110
Community Higher Education Bursaries Formally Awarded162
Recognition of Prior Learning (RPL) Matrix Certifications279
Total Corporate Service Training Reach3,559
Skills Development · 2011/12 & 30 June 2012
Management levelGenderNumber in post at 30 June 2012Target 30 June 2011Actual 30 June 2011Target 30 June 2012Actual 30 June 2012Skills programmes & Learnerships Target 30 June 2011Skills programmes & Learnerships Actual 30 June 2011Other short courses Target 30 June 2012Other short courses Actual 30 June 2012
MM and S57*Female
MM and S57*Male
Councillors, senior officials and managersFemale209183102108183
Councillors, senior officials and managersMale402302212241302
Technicians and associate professionalsFemale8324242415795270181119
Technicians and associate professionalsMale1003148148148151149393299297
ProfessionalsFemale602304129687304129
ProfessionalsMale4628615859186158
Total27611721721721183845229013551017
Occupational Classification & GenderOriginal BudgetActual Outlay SpendTotal Employees at Start of YearLearnershipsOther Forms of TrainingSkills Programmes & Short Courses
MM and S57* — Female2007
MM and S57* — Male
Legislators, Senior Officials & Managers — Female4892,1392,9841,2636,0063,912
Legislators, Senior Officials & Managers — Male7843,5953,0483,4468,0473,084
Professionals — Female8402,9364,2826,4649,0003,943
Professionals — Male9461,1611,3183,3885,0916,186
Technicians & Associate Specialists — Female5025,4854,1521,3778,5801,338
Technicians & Associate Specialists — Male9752,4644,5953,6169,2985,812
Administrative Clerks — Female4711,0241,3041,0204,6065,565
Administrative Clerks — Male8731,8721,8207,4571,4328,147
Service Workers & Public Safety — Female9732,9262,1799,3095,3252,432
Service Workers & Public Safety — Male8812,42415460871,523
Plant & Machine Operators & Assemblers — Female8441,9262,3945,90984431
Plant & Machine Operators & Assemblers — Male3131,2871,6129,7311,1013,035
Elementary Occupations — Female6513,1143,7849,7496503,830
Elementary Occupations — Male5761,271304,3849,14943,384
Consolidated Portfolio Total12,07130,38443,38496,282
Source: Annual Report 2011/12 — Tables 91–93, Chapter 3.26 Human Resource Services Audit Review
ICT Staff · 2010/11–2012/13
Job Level2010/11 EmployeesPosts2011/12 Employees2012/13 EmployeesVacancies (fulltime equivalents)Vacancies (% of total posts)
0-3111000%
4-621232017313%
7-9415545401018%
10-1210110592801312%
13-15185191181175105%
16-188691858267%
19-20
Total410428396364327%
Job Level2010/11 EmployeesPosts2011/12 EmployeesVacancies (fulltime equivalents)Vacancies (% of total posts)
0-3090731719%
4-61576601621%
7-9271410429%
10-1212257461119%
13-1581101000%
16-1811176343%
Section 5791889%
Total3562632065922%
Job Level2010/11 EmployeesPosts2011/12 EmployeesVacancies (fulltime equivalents)Vacancies (% of total posts)
0 - 3172601217%
4 - 6381311112015%
7 - 91442217523%
10 - 125295831213%
13 - 15863833513%
16 - 181281711635%
Section 5754120%
Total4493803196116%
Job Level2010/11 EmployeesPosts2011/12 EmployeesVacancies (fulltime equivalents)Vacancies (% of total posts)
0 - 30000
4 - 6105500%
7 - 9304400%
10 - 1232925414%
13 - 1562200%
16 - 181157853%
Section 5791889%
Total5064442031%
Job Level2013/2014 Employees2013/2014 Posts2014/2015 Employees2014/2015 Vacancies2014/2015 Vacancies %
0 - 32
4 - 635
7 - 933
10 - 1269
13 - 1523
16 - 180
Section 575
Total1673452935215.07%
ICT Services · 2017/18 & 2011/12 Baseline
Total ICT Posts 2017/18
183
ICT Employees 2017/18
126
Vacancy Rate
31%
ERP Modules Live
5
vs 4 target
Broadband Fibre Rolled Out
200km
Wi-Fi Sites Deployed
200
Service Delivery App
Phase 2
ICT Operational Expenditure
R406m
Objective2016/17 Target2016/17 Actual2017/18 Target2017/18 Actual2018/19 Target
Enterprise Resource Planning (ERP modules)4 modules4 modules4 modules5 modules5 modules
Broadband Fibre Rollout (km)200km156km200km200km200km
Wi-Fi Rollout (sites)200 sites0200 sites200 sites200 sites
Service Delivery App (phase)Phase 1Phase 1Phase 1Phase 2Phase 3
Job LevelPostsEmployees 2016/17Vacancies 2016/17Employees 2017/18Vacancies 2017/18Vacancy %
0–3110100%
4–6493415341531%
7–9665412541218%
10–12281810181036%
13–152315815835%
16–187252571%
19–209363667%
Total183126571265731%
Detail2016/17 Actual2017/18 Orig Budget2017/18 Adj Budget2017/18 ActualVariance
Total Operational Revenue1,661201201100%
Employees94,154110,700109,96290,918-22%
Repairs and Maintenance139,636142,461141,661168,242+15%
Other159,809194,514195,052147,074-32%
Total Operational Expenditure393,599447,676446,676406,235-10%
Net Operational Expenditure391,939447,676446,475406,033-10%
Source: Annual Reports 2011/12 & 2017/18 — ICT Services chapters. The full 2010/11–2012/13 ICT staff organogram (all job levels) appears under Human Resources.
Roads, Transport & Stormwater Drainage · Strategic Framework
Passenger Journeys 2016/17
68,005
Active Fleet Size
108
Journeys Cancelled
47
Target benchmark: 25
BRT Core Constructed
2.5km
BRT Stations Built
6
Non-Motorised Paths
11km
Total Tarred Roads 2015/16
8,085km
Transport Capex 2016/17
R513m
Road Network Infrastructure · Time Series (2009/10–2015/16)

Total Tarred Roads Network · 2009/10–2015/16 (km)

Road Construction & Maintenance Costs · 2010/11–2015/16 (R thousand)

Financial YearTotal Tarred Roads (km)New Tarred Roads (km)Existing Tarred Roads Resurfaced (km)Tarred Roads Maintained (km)
2009/107,456136106
2010/117,59294255
2011/127,68657175
2012/137,906105217217
2013/147,99993119119
2014/158,02425554554
2015/168,08561139139
Financial YearTotal Gravel Roads (km)New Gravel Roads ConstructedGravel Roads Upgraded / Tarred
2009/10136
2010/1198094
2011/1298057127
2012/13980105217
2013/1498093108
2014/151,20025343
2015/161,200611,148
Financial YearNew GravelGravel — TarredNew Tar MaintainedRe-workedMaintainedMaintained Tar
2011/12129,0007,6278,8230198,686
2012/13393,34220,608097,87798,847
2013/14404,9513,0540112,664185,817
2014/15173,25528,281173,255034,280
Operational Efficiency Matrix Detail2015/16 Actual2016/17 Estimate2016/17 Actual2017/18 Estimate
Passenger Journeys Logged (Count)63,33271,01068,00570,752
Total Scheduled Seat Capacity Available4,116,5804,376,2754,420,3254,180,800
Active Bus Fleet Count (Year-End)104120108108
Total Scheduled Bus Journeys63,33271,01066,49969,150
Scheduled Journeys Cancelled (Deficit)23254725
Proportion of Scheduled Journeys Cancelled4%4%7%4%
Financial Component Summary2015/16 Actual2016/17 Orig Budget2016/17 Adj Budget2016/17 ActualVariance vs Orig Budget
Total Directorate Operational Revenue902,402911,044835,044745,708-22%
Employee Compensation Costs251,617324,504320,010254,869-27%
Asset Repairs & Infrastructure Maintenance24,80631,21417,98031,2450%
Other Operational Contracted Overheads77,344743,823628,290556,526-34%
Total Departmental Operational Expenditure353,7681,099,541966,280842,640-30%
Net Fiscal Operational Expenditure Position-548,634188,497131,23696,932-94%
ProjectBudgetAdj BudgetActualVariance
Total All (as reported)683,800717,800685,5890%
Aerotropolis: Rhodesfield Rd Network5,0005,0004,9980%
Alberton Depot Female Ablution & Change Rooms1,000296100%
Atlasville Spruit Flood Management5005515489%
Bdfv & Edvl, Geometric Impr., AG de Witt/Kloof Butterfly800699100%
Bdfv & Edvl, Geometric Impr., Harper Road Bridge1,000400357-180%
Bdfv & Edvl, Geometric Impr., Riley Road RAMP1,000400357-180%
Bedfordview SW Protection3,0003,0023,0000%
Benoni, Const of SW Outfall Rynfild3003003000%
Bergrivier Drive: Reconstruction & Widening3,0005,0464,76637%
Boksburg New Roads Depot1,000937100%
Constr. of Small Holding Roads (East) Acron & Jarrah6,0006,0105,876-2%
Constr. of Small Holding Roads (East) Gum Road5,0005,0005,0000%
Construct Daveyton CBD/N12 Interchange8,0001,170823-872%
Construction of Roads Tembisa Ext 113,0003,0002,451-22%
Construction of Roads Umtahmbeka3,0003,8603,82922%
Doubling Barry Marais Road3,0003,0002,9990%
Eastleigh Spruit Channel10,0004,3504,297-133%
Elandsfontein SW Implementation500500487-3%
Extension of Albertina Sisulu Expressway3,000703663-352%
Germiston Depot Standby Quarters, Ablutions4,5524,551100%
Hewlitt Drive Intersection6,0003,4833,107-93%
ICT Equipment1,0001,000771-30%
Implementation of Roads Master Plan: Comet Area8,0008,0008,0000%
Isandovale, Erosion Protection Impl (North)1,5005050-2900%
K136 & Rd 1894 Link Road8,0008,0007,9970%
Kaal Spruit Rehabilitation15,0002,8002,311-549%
Kraft Barbara Road Intersection Upgrade10,00010,70010,6586%
Kwa-Thema Stormwater2,0002,0002,0000%
Leachville Roads & Stormwater3,0003,0103,0100%
Minor Works for Roads and SW: South1,0006,7883,60072%
Monument Road12,00013,00012,7526%
Pappariche Legal Settlement Roads and Stormwater8,1908,187100%
This is an alphabetical project register running to 150+ line items in the source (2017/18 AR, Table 67); the 32 largest/earliest-alphabetical projects shown above sum to a fraction of the R683.8m total — remaining smaller projects (mostly sub-R1m stormwater and paving line items) are not itemized here but are available on request.
Roads & Stormwater Workforce · 2011/12
Job LevelPosts (T-scales)Posts (X-scales)Employees (FTE)VacanciesVacancies (%)
0 - 34825534975610.13%
4 - 61562061673918.93%
7 - 966847778.33%
10 - 126384701416.67%
13 - 15364741612.77%
16 - 18797222.22%
Section 57474342.86%
Total81499086312712.83%
Stormwater Performance · 2017/18–2019/20

Stormwater · New Measures vs Maintained km

Stormwater · Cost (R'000)

Source: Annual Reports 2009/10–2015/16 (roads baseline), 2011/12 (workforce & cost detail), 2016/17 (transport ops), 2017/18–2019/20 (capex & stormwater)
Health & Social Development · 2016/17
Total Operational Revenue
R196m
2016/17 actual
Total Operational Expenditure
R899m
Net Expenditure
R703m
Employee Cost
R666m
-10% vs budget
Capex Budget
R88.8m
Capex Actual
R81.8m
Older Persons in Programmes
7,244
vs 5,500 target
ECD Practitioners Trained
5,468
vs 900 target
Child Care, Aged Care & Social Programmes · Service Statistics
Indicator2015/16 Target2015/16 Actual2016/17 Target2016/17 Actual2017/18 Target2018/19 Target
Older persons (60+) in active ageing programmes5,5006,7195,5007,2445,9006,000
Children 7–14 reached with behaviour change programmes7,00010,8517,0008,3747,6007,700
Youth 15–35 reached with behaviour change programmes8,20010,1378,20012,3618,6008,700
ECD practitioners trained in skills development9002,2769005,4681,7001,800
Detail2015/16 Actual2016/17 Orig Budget2016/17 Adj Budget2016/17 ActualVariance
Total Operational Revenue226,169196,245196,843196,0430%
Employees629,981733,257757,691665,818-10%
Repairs and Maintenance14,22810,71711,36020,473+48%
Other172,094193,027198,699212,549+9%
Total Operational Expenditure816,302937,001967,750898,840-4%
Net Operational Expenditure590,133740,756770,907702,798-5%
Job LevelPosts 2015/16Employees 2015/16Posts 2016/17Employees 2016/17VacanciesVacancy %
0–3111100%
4–62727262613.7%
7–9111100%
10–124141393924.9%
13–151616161600%
16–18122200%
Section 57111100%
Total8889868633.4%
ProjectBudgetAdj BudgetActualVariance
Total All88,80082,61381,790-9%
Air Conditioners — Health Facilities200100920%
Early Childhood Development Centre (1)6,0007,5007,496+20%
Early Childhood Development Centre (2)6,0006,2506,2500%
Early Childhood Development Centre (3)6,0006,2506,250+4%
Extension & Upgrade — Esangweni Clinic13,00017,41417,414+25%
Extension & Upgrade — Selope Thema Clinic7,0006,5166,515-7%
ICT Equipment6,5006,8236,819+5%
New TSIETSI Clinic — Phomolong South5,0003,3843,384-48%
New Crystal Park Clinic4,0001,7811,7810%
New Dukatole Clinic4,0003,5863,586-12%
New Khumalo Clinic4,5003,1623,162-42%
Office Furniture (Health Dept)4,0003,1653,147-27%
Specialised Vehicles3,6003,5733,573-1%
Source: Annual Report 2016/17 — Health & Social Development
Planning, Development & LED · 2017/18
Building Plans Received
20,832
Plans Approved
13,657
value R11.3bn
Projects Completed
4,681
value R6.9bn
Total Inspections
83,251
74% of projected
Total Notices Issued
4,700
Building Control Revenue
R33.4m
92.1% of budget
YoY Plan Submissions
+5,090
15,742 → 20,832
Capex Spend (EPMO)
88.56%
vs 95% target
DescriptionValue
Building plan applications received20,832
Income generated from applicationsR31,150,296.45
Building plans approved13,657
Value of approved plansR11,288,467,122.88
Building projects completed4,681
Value of completed projectsR6,855,721,291.82
MonthTotal EMMDistrict ADistrict BDistrict C
Jul-17R2,499,398R1,597,282R1,046,524R855,592
Aug-17R4,299,950R4,298,366R1,813,341R1,002,955
Sep-17R2,203,473R2,242,586R449,775R1,211,112
Oct-17R2,552,679R1,816,678R1,075,408R795,593
Nov-17R3,565,421R3,301,852R1,196,365R1,338,870
Dec-17R1,503,990R1,005,002R550,537R548,451
Jan-18R2,223,827R2,037,258R807,751R878,819
Feb-18R3,007,456R2,672,861R1,384,653R949,942
Mar-18R3,130,870R2,581,056R1,339,446R1,110,368
Apr-18R2,851,590R2,286,680R1,197,820R825,090
May-18R2,542,479R1,922,275R662,689R1,287,514
Jun-18R3,011,174R3,328,847R1,048,845R1,129,482
Total 2017/18R33,392,307R28,534,365R12,573,153R11,937,789
QuarterEMM TotalNorthSouthEast
Q121,1785,3608,4847,334
Q220,2484,7856,8058,658
Q320,4945,8707,7436,881
Q421,3315,3898,5777,365
Total83,251
Projected112,896
% Conducted74%
DepartmentIndicatorTargetActualVarianceRating
Water & SanitationKm of water/sewer pipes replaced/extended30km41.75km+11.75kmAchieved
Water & SanitationAdditional HHs in formal dwellings with sewer connections1,2002,284+1,084Achieved
Water & SanitationAdditional megalitres reservoir storage450-45Not Achieved
Customer Relations% customer queries resolved90%94.9%+4.9%Achieved
EPMOCapex spend % by departments95%88.56%-6.44%Not Achieved
EnergyUnaccounted electricity12.2%11.8%+0.2%Achieved
Finance% of amounts billed collected94%93.10%-0.9%Not Achieved
Finance% of tenders processed within timeframe85%89.06%+4.06%Achieved
FinanceAudit opinionClean AuditUnqualifiedNot Achieved
Waste Management Services · 2015/16 Operational Performance
Strategic Service Delivery IndicatorTarget 2014/15Actual 2014/15Target 2015/16Actual 2015/16
Landfill sites compliant with permit conditions (No.)4554
240L Wheelie Bins rolled out to households (No.)52,62344,00044,00041,367
Households in formal areas with weekly kerb-side removal652,498706,668100%100%
Additional RDP households with refuse removal access3,47355,575100%100%
Waste recycled as % of total volume disposed16.2%3%7%22%
Informal settlements with refuse removal access (No.)119119119119
Source: Annual Reports 2015/16 & 2017/18 — Planning, LED & Waste Management chapters
Land Use Development · 2013/14–2014/15
DetailRezoning 2013/14Rezoning 2014/15Built Environment 2013/14Built Environment 2014/15Formalization of Townships 2012/13Formalization of Townships 2014/15
Planning application received3422311,14911,075
Determination made in year of receipt3316,4789,109
Determination made in following yearTBDTBDTBDTBD
Applications withdrawn0500
Applications outstanding at year end3034734,6711,966
Service ObjectiveOutline Service TargetsYear -1 TargetYear 0 TargetYear 0 ActualYear 1 TargetYear 1 ActualYear 2 TargetYear 3 Target
% of development applications complying with town planning policies and legislationIncreased efficiency with respect to the application process92%92%91.75%100.00%92%93%94%
% of land affected by geotechnical hazards rehabilitatedIncreased rehabilitation of land affected by geotechnical hazards80%68%80%80%80%80%80%
% of municipal capital budget invested in geographic priority areasIncreased investment of municipal capital budget in geographic priority areas60%0%60%68%60%60%60%
Governance, Risk Management & Procurement · 2016/17 Framework
Risk Profiles Reviewed
30
Directorate audits
Risk Maturity Level
Level 2
Target: Level 3 deficit
Insurance Audits
4
Fiduciary oversight
Land Parcels Banked
15
Properties Refurbished
9
Total Procurement Spend
R11.6bn
Open bids & quotes
HDI-Owned Allocations
R3.68bn
31.7% of total wallet
Local CoE In-Region Spend
R3.30bn
28.4% of procurement
Procurement Expenditure Breakdown · 2016/17 Allocations
Socio-Economic Award Transformation CategoryAudited Expenditure Outlay (R)
Total Consolidated Procurement (Open Bids & Quotes > R30k)11,612,021,693
Companies 100% Owned by Historically Disadvantaged Individuals (HDIs)3,680,266,451
Black Women-Owned Enterprises (≥30% Equity Threshold)1,291,699,373
Total Women Equity Footprint (Including Broad-Based Classifications)2,766,088,526
Youth-Owned & Managed Entities1,549,068,119
Localized Enterprises (Geographically Based Within Ekurhuleni Region)3,303,121,369
Strategic Key Performance IndicatorsUnit2015/16 Actual2016/17 Target2016/17 Actual2017/18 Target
Land parcels banked for future municipal development useNo.1501520
Properties whose asset refurbishment cycles are fully completedNo.9799
Strategic land parcels approved for development/investment accessNo.32282432215
Revenue growth expansion margin from strategic property transactions%5%5.60%5%5%
Directorate operational risk profiles comprehensively reviewedNo.30303030
Risk Maturity Level designation achievedLevelLevel 2Level 3Level 24
Comprehensive compliance insurance audits undertakenNo.4444
Financial Component Summary2015/16 Actual2016/17 Orig Budget2016/17 ActualVariance vs Orig %
Total Directorate Operational Revenue0%
Employee Compensation Costs5,76518,84418,962-65%
Asset Repairs & Infrastructure Maintenance4100%
Other Operational Contracted Overheads3,7242,1063,426+35%
Total Departmental Operational Expenditure9,49020,94922,388-43%
Net Fiscal Operational Expenditure Position9,49020,94922,388-43%
Governance Structure · 2017/18
Position / DepartmentPersonStatus
City ManagerDr Imogen MashaziFilled
Chief Operating OfficerLesiba (Joe) MojapeloFilled
Chief Financial OfficerGugu MalazaFilled
Chief Risk OfficerActing (HOD)Vacant
Chief Audit ExecutiveActing (HOD)Vacant
City PlanningMotubatseFilled
Communications & Brand ManagementRego MavimbelaFilled
Economic DevelopmentCaiphus ChaukeFilled
EMPD (Metro Police)Isaac MapiyeyeFilled
EnergyMark WilsonFilled
Environmental Resource & Waste ManagementFaith MathibideFilled
Health & Social DevelopmentDr Gilbert MotlatlaFilled
Human Resources Management & DevelopmentNaledi ModibediFilled
Human SettlementsBongani MolefeFilled
Information Communication TechnologyTumelo KgananeFilled
Roads & Storm WaterSizwe CeleFilled
Sports, Recreation, Arts & CultureVincent CampbellFilled
Transport, Planning & ProvisionLusanda MadikizelaFilled
Water & SanitationMduduzi ShabanguFilled
Award CategoryAmount (R)%
CoE-based companies4,137,831,37438.58%
Non-CoE-based companies6,588,296,45461.42%
Total10,726,127,827100.00%
Project Infrastructure DesignationOriginal BudgetAdjusted BudgetActual Capex SpendVariance vs Adj %
Total Consolidated Risk Capital Portfolio3243243230%
Corporate Infrastructure ICT Equipment Terminals2502342340%
Directorate Station Office Furniture Asset Allocations709089+21%
Other Ancillary Support Service Equipment Operations40%
Source: Annual Report 2016/17 — Fiduciary Performance Framework, Property, Legal, Risk Management & Procurement. Annual Report 2017/18 — Governance & Procurement